Victoria Park Stadium: The Brisbane 2032 Main Venue
The Brisbane 2032 main stadium is being built at Victoria Park in Herston, about two kilometres north of the CBD. It will seat 63,000 for the Games and host the opening and closing ceremonies and the athletics. Early works started in August 2026. Completion has been reported as targeted for 2031, though no formal date has been published.
TL;DR
- Where: Victoria Park, Herston — parkland, two kilometres north of the CBD.
- Size: 63,000 for the Games, up to about 70,000 for concerts. MCG-sized field of play.
- Status: early works underway since August 2026. Bulk earthworks late 2026 into early 2027.
- Cost: reported around A$3.8 billion, inside a A$7.1 billion Games infrastructure programme.
- Name: unresolved. IP Australia rejected the ‘Brisbane Stadium’ trademark.
Where is the Victoria Park stadium?
Victoria Park sits in Herston, immediately north of Spring Hill and about two kilometres from the Brisbane CBD. It is walkable from the city in roughly half an hour, and a few minutes by train or bus.
The site is parkland, and that is the reason this was the most argued-over decision of the whole Games build. Brisbane is not clearing an industrial site or rebuilding an existing ground. It is putting a 63,000-seat stadium on public open space, and a meaningful part of the local opposition has been about exactly that rather than about the Olympics.
What will be held there during Brisbane 2032?
The opening and closing ceremonies, and the athletics programme. The Paralympic opening and closing ceremonies are scheduled here too, between 24 August and 5 September 2032.
If you only get to one venue during the Games, this is the one that will define what people remember of Brisbane 2032. It is also the venue where tickets will be hardest to get and most expensive, on the evidence of every recent Games.
How big will it be?
63,000 seats in Games configuration, and up to roughly 70,000 for concerts. The field of play is being sized to MCG dimensions, which is a deliberate decision about the next fifty years rather than the three weeks in 2032: it means the venue can take cricket and Australian rules football afterwards.
For comparison, Suncorp Stadium holds about 52,500 and the Gabba about 42,000. This will be comfortably the largest stadium in Queensland.
Has construction actually started?
Yes, though not the part that looks like construction. The Games Independent Infrastructure and Coordination Authority took possession of the site on 1 June 2026, and early works began in August. That phase means site investigation, demolition of existing infrastructure in the way, and building the compounds and access roads a project this size needs before real work can start.
Walk past the Herston edge of the park today and you will see hoarding and closed pathways, not cranes. Sections of the parkland have been closed to the public since June. That is normal for this stage, and it is why the project can look static from outside while a great deal is being settled.
Federal environmental approval was granted in May 2026, which cleared the largest remaining regulatory hurdle. Architects were appointed in January 2026 and design is well advanced.
When will it be finished?
Here is where the record gets thinner than anyone would like.
| Stage | Timing | Status |
|---|---|---|
| Architects appointed | January 2026 | Done |
| Federal environmental approval | May 2026 | Done |
| Site handover to GIICA | 1 June 2026 | Done |
| Early works begin | August 2026 | Underway |
| Early-works contract awarded | Coming months | Pending |
| Bulk earthworks | Late 2026 – early 2027 | Scheduled |
| Main construction | Not published | Unconfirmed |
| Completion | Reported as 2031 | Unconfirmed |
| Games open | 23 July 2032 | Fixed |
A 2031 completion has been reported, which would leave a year of buffer for test events and fit-out before the Games. No formal completion date has been published to confirm it.
The thing worth watching: the gap between bulk earthworks starting in late 2026 and any published completion date. A stadium of this scale typically needs four to five years of main construction. Working back from July 2032, the schedule has room but not a lot of it. Any slip in the earthworks start is the first real warning signal, and it will show up long before anyone announces a delay.
What will it be called?
Not settled, and more interesting than it sounds. Queensland applied to trademark ‘Brisbane Stadium’ specifically so the name could never be sold to a corporate sponsor. IP Australia refused the application: you cannot register a place name plus a common noun.
So the name stands for now, but it rests on political commitment rather than legal protection, and a future government is not bound by it. Worth remembering when the naming-rights conversation starts, because it will.
How do you get to Victoria Park?
It is one of the easier venues to reach. Herston is served by bus, the CBD is a half-hour walk or a few minutes on public transport, and Cross River Rail adds four new inner-city stations that will change how people move around the north side.
Games-time transport arrangements have not been published. Whether a ticket includes free public transport, as it has at several recent Olympics, has not been confirmed either way.
Where should you stay near the stadium?
Herston and Spring Hill are the closest options, both walkable. The CBD and Fortitude Valley are a short hop. Nothing is bookable for the Games period yet, because hotels do not release that inventory until roughly 12 to 18 months out.
The more useful question six years out is whether enough rooms will exist at all. Queensland is running roughly 14,700 rooms short of what the Games need.
What happens to it after 2032?
It takes over from the Gabba as Brisbane's main cricket and football ground. That is the whole argument for the MCG-sized field of play, and it is the answer the Queensland government gives when asked why a new build made more sense than a Gabba rebuild.
Whether that works out is the open question of the next decade. Olympic stadiums have a poor record as long-term assets when the after-use is an afterthought. This one at least has the after-use designed in from the start.
What changed in 2026
2026 was the year Victoria Park stopped being an argument and became a construction site. Environmental approval in May, site handover on 1 June, early works from August, and architects on board since January.
What has not changed: no published completion date, no awarded early-works contract as of September, and no resolution on the name.
Frequently asked questions
Where is the Brisbane 2032 Olympic stadium?
Victoria Park, in Herston, about two kilometres north of the Brisbane CBD. It is a new build on parkland, confirmed after the March 2025 venue reset dropped the plan to rebuild the Gabba.
How big will the Victoria Park stadium be?
63,000 seats for the Games, up to roughly 70,000 in concert configuration. The field of play is MCG-sized so the venue can take cricket and Australian rules football after 2032.
Has construction started on the Brisbane 2032 stadium?
Yes, but not the main build. GIICA took possession of the site on 1 June 2026 and early works began in August 2026 — site investigation, demolition and construction compounds on the Herston side. Bulk earthworks are scheduled for late 2026 into early 2027.
When will the Victoria Park stadium be finished?
Completion has been reported as targeted for 2031, a year before the Games, but no formal date has been published. A stadium this size usually needs four to five years of main construction, so the schedule has room without much slack.
What will be held at the stadium during Brisbane 2032?
The Olympic opening and closing ceremonies and the athletics, plus the Paralympic opening and closing ceremonies between 24 August and 5 September 2032.
What will the Brisbane 2032 stadium be called?
Not settled. Queensland applied to trademark ‘Brisbane Stadium’ so the name could not be sold to a sponsor. IP Australia rejected it, because a place name plus a common noun is not registrable. The name now rests on political commitment rather than law.
How much is the Victoria Park stadium costing?
Reported at about A$3.8 billion, inside a A$7.1 billion Games infrastructure programme. That is a public estimate, not a final contracted cost, and the early-works contract had not been awarded as of September 2026.
Is the Gabba still being used for Brisbane 2032?
The plan to rebuild the Gabba as the main stadium was dropped in the March 2025 venue reset after a review found it unworkable on cost and timing. Victoria Park replaced it, and the new stadium is meant to take over from the Gabba afterwards.
Sources: Games Independent Infrastructure and Coordination Authority · IP Australia · Brisbane 2032 Organising Committee · Queensland Government venue review, March 2025.
More: the full Brisbane 2032 guide · every confirmed venue · why the stadium trademark was rejected · the latest from the site
BRIS2032 — Independent Coverage