Victoria Park Stadium: What's Actually Happening On Site
Something is finally happening at Victoria Park. After years of argument about whether Brisbane should build a new stadium at all, early works commenced in August 2026. The Games Independent Infrastructure and Coordination Authority took possession of the site on 1 June, and the work underway now is site investigation, enabling works, demolition of some existing infrastructure, and setting up construction areas on the Herston side of the park. Sections of the parkland there have been closed to the public since June. Bulk earthworks, the point at which the site starts to look like a build rather than a survey, are scheduled for late 2026 to early 2027. No completion date has been published.
- Early works started August 2026. GIICA took the site on 1 June.
- Right now: site investigations, enabling works, demolition, construction compounds — Herston side.
- Bulk earthworks late 2026 to early 2027. Early-works contract due to be awarded shortly.
- 63,000 seats for the Games, up to about 70,000 for concerts. Field of play sized like the MCG.
- Reported at about $3.8 billion, within a $7.1 billion Games infrastructure program.
- Hosts the opening and closing ceremonies and athletics, then becomes Brisbane's main stadium.
What is physically on the site right now?
Fences and survey crews, essentially. The current phase is deliberately unglamorous: investigating ground conditions, removing existing infrastructure that's in the way, and building the compounds and access that a project this size needs before real construction can start.
If you walk past the Herston edge of the park today, what you'll see is hoarding and closed pathways rather than cranes. That's normal for this stage, and it's the reason the project can look static from outside while a lot is being decided.
What happens next, and when?
| Stage | Timing | Status |
|---|---|---|
| Site handover to GIICA | 1 June 2026 | Done |
| Early works begin | August 2026 | Underway |
| Early-works contract awarded | Coming months | Pending |
| Bulk earthworks | Late 2026 – early 2027 | Scheduled |
| Main construction | Not published | Unconfirmed |
| Completion | Not published | Unconfirmed |
| Games open | 23 July 2032 | Fixed |
What is actually being built?
A 63,000-seat stadium, with concert configurations reported up to around 70,000, and a field of play equivalent in size to the MCG. The design is by Australian firms Cox Architecture and Hassell with Japanese group Azusa Sekkei — the same names behind Perth's Optus Stadium and redevelopments at the Adelaide Oval and the MCG.
Released designs show shaded seating, large digital screens and a cantilevered roof. The stadium sits in a central position near Gilchrist Avenue, positioned to connect to existing transport rather than sit isolated in the parkland.
How much is it costing?
About $3.8 billion on current reporting, inside a $7.1 billion Games infrastructure program. That figure has moved during planning, so it's worth treating any single number as the current published position rather than a settled cost.
For context on why this is contentious: the LNP went to the 2024 state election promising not to build a new stadium for the Games. Premier David Crisafulli has since apologised for breaking that commitment. The stadium was recommended by GIICA in its 100-day review of Games infrastructure.
What about the park itself?
Sections on the Herston side closed on 1 June and more closures are expected as the build progresses. The community group Save Victoria Park continues to oppose the project, arguing the green space should be preserved. The Gabba, once earmarked as the main stadium under the previous government, is now set to be demolished after 2032 for urban renewal.
Staying near the stadium
Spring Hill sits on the northern edge of the CBD, closest to the Victoria Park precinct and walkable to the city. It's the handiest base for ceremony and athletics days.
Check Spring Hill stays →Affiliate link. If you book through it we may earn a small commission, at no extra cost to you. It keeps BRIS2032 independent.
FAQ
Has construction actually started?
Yes. Early works commenced in August 2026, after GIICA took possession of the site on 1 June. That means investigations, enabling works and demolition rather than stadium construction proper.
When will it be finished?
Not published. Bulk earthworks are scheduled for late 2026 to early 2027. The venue must be ready ahead of the Games opening on 23 July 2032.
How much does it cost?
About $3.8 billion on current reporting, within a $7.1 billion Games infrastructure program. Figures have shifted during planning.
How many seats?
63,000 for the Games, with concert configurations reported up to around 70,000.
Is Victoria Park still open?
Partly. The Herston side has been closed since 1 June 2026. Further closures are expected as work progresses.
Who designed it?
Cox Architecture and Hassell with Azusa Sekkei — the firms behind Optus Stadium and works at the Adelaide Oval and MCG.
What happens to the Gabba?
It is set to be demolished following the 2032 Games to make way for urban renewal.
Independent coverage by Toby Edmanson, BRIS2032. We update this page as construction milestones are confirmed. Photos: Kyethepie21 / Wikimedia Commons (CC0) — no attribution legally required, credited anyway.